Huu Nghi 2 Cement Plant project.

 The project has been pushed up since the third quarter 2010. The current fluctuation of interest rate made us defer our equipment buying till August 2011. The experimental installs are expected to be run in 5 months. The company has completed : scraping 3 limestone and clay mines ; digging 25m deep to create the peak pillar, storing all the limestone and clay exploited in the valleys; setting up an electric transformer station, completing the internal road. The first stage is exoected to be finished in the 4th quarter 2011.

Total capital of this project is VND 68.500.000.000 in which 2.172.000.000 raised by our employees.